Optimizing Project Duration and Cost of Support Ship through Time-Cost Trade-Off Analysis and Microsoft Project Application: A Case Study at PT XYZ

  • Firda Amalia Putri Progam Studi Teknik Industri, Fakultas Teknik dan Sains, Universitas Pembangunan Nasional Veteran Jawa Timur
  • Isna Nugraha Progam Studi Teknik Industri, Fakultas Teknik dan Sains, Universitas Pembangunan Nasional Veteran Jawa Timur
Keywords: Microsoft project; Optimization; Time cost trade off method

Abstract

The construction of a ship project requires time control to avoid delays because late fines will be imposed. This control can be carried out using project management control tools, namely project scheduling. This research aims to optimize project duration and costs by finding the critical path using the help of Microsoft Project Software and accelerating to avoid project delays using the time cost trade off method. The data collection method was carried out by interviews and direct observation at the project location and obtained through PT XYZ internal parties. The research results showed that there was a delay of 12 days on the Support Ship construction project with 10 critical activities on the production floor. Alternative acceleration is done by adding working hours (overtime) by 2 hours, 3 hours and 4 hours. After calculating the acceleration for critical activities that have the lowest cost slope values, The optimal duration and costs were obtained by adding 3 hours of overtime so that the processing time could be accelerated from 236 days to 228 days with a total acceleration cost of IDR 53,295,000.

Downloads

Download data is not yet available.

References

R. C. . Kiling, A. K. T. Dundu, and J. B. Mangare, “Perataan Tenaga Kerja Pada Proyek Pembangunan Dengan Menggunakan Program Microsoft Project 2016 ( Studi Kasus : Kos Kalyana Paal 2 ),” J. Tekno, vol. 17, no. 73, pp. 97–103, 2019.

M. Fazis and Tugiah, “PERENCANAAN PROYEK DAN PENJADWALAN PROYEK,” J. Sos. dan Teknol., vol. 2, no. 12, pp. 1365–1377, 2022.

S. Hartmann and D. Briskorn, “An updated survey of variants and extensions of the resource-constrained project scheduling problem,” Eur. J. Oper. Res., vol. 297, no. 1, pp. 1–14, 2022, doi: 10.1016/j.ejor.2021.05.004.

A. L. Tengker, “PERATAAN TENAGA KERJA DENGAN MENGGUNAKAN MICROSOFT PROJECT PADA PROYEK REHABILITASI PUSKESMAS MINANGA,” J. Sipil Statik, vol. 7, no. 10, pp. 1261–1268, 2019.

D. Isnubroto and C. K. Putri, “ANALISIS PENJADWALAN DAN ALOKASI SUMBER DAYA PADA PROYEK KONSTRUKSI MENGGUNAKAN MICROSOFT PROJECT (Studi Kasus Pekerjaan Struktur Proyek XYZ),” Wahana Tek. SIPIL, vol. 26, no. 1, pp. 52–65, 2021.

P. L. A. Luthan, N. Sitanggang, A. Hamid, and B. Hadibroto, “Use of the bar chart/S-curve and computerized precedence diagram method on scheduling and controlling building construction projects by contractors : a cross-sectional study,” F1000Research, vol. 10, pp. 1–14, 2022.

S. Atin and R. Lubis, “Implementation of Critical Path Method in Project Planning and Scheduling,” in IOP Conference Series: Materials Science and Engineering, IOP Publishing, 2019, pp. 22–31. doi: 10.1088/1757-899X/662/2/022031.

S. Romadhona, F. Kurniawan, and J. Tistogondo, “Project Scheduling Analysis Using the Precedence Diagram Method ( PDM ) Case Study : Surabaya ’ s City Outer East Ring Road Construction Project ( Segment 1 ),” Int. J. Eng. Sci. InformationTechnology, vol. 1, no. 2, pp. 53–61, 2021.

Y. A. Irawan, Suharto, and A. Juara, “Analisa Optimasi Biaya Dan Waktu Metode TCTO (Time Cost Trade Off) (Study Kasus : Preservasi Jalan Ruas Sp . Gunung Kemala – Sanggi),” J. Civ. Eng. Study, vol. 02, no. 02, pp. 60–67, 2022.

A. Muharani, I. P. Mulyatno, and S. Jokosisworo, “Optimasi Percepatan Proyek Pembangunan Kapal Kelas I Kenavigasian dengan Metode Pendekatan Analisa Time Cost Trade Off,” J. Tek. PERKAPALAN, vol. 8, no. 3, pp. 330–338, 2020.

P. A. Sepang, T. T. Arsjad, and G. Y. Malingkas, “Perataan Sumber Daya (Cash Flow) Proyek Konstruksi Menggunakan Aplikasi Microsoft Project Pada Pembangunan Gedung Balai Kesehatan Ibu Dan Anak Kota Manado,” J. TEKNO, vol. 21, no. 85, pp. 1737–1745, 2023.

Rizal, P. T. Juwono, and R. Haribowo, “Studi Manajemen Konstruksi Proyek Rehabilitasi Bendungan Simo di Kabupaten Grobogan dengan Menggunakan Program Microsoft Project Manager 2016,” J. Teknol. dan Rekayasa Sumber Daya Air, vol. 2, no. 1, pp. 28–40, 2022.

A. A. S. Prakosa, R. Rochmoeljati, and I. Nugraha, “ANALISIS KUALITAS DEFECT PRODUK PUPUK DOLOMIT DENGAN METODE NEW SEVEN TOOLS DAN FAILURE MODE AND EFFECT ANALYSIS ( FMEA ) DI PT . XYZ,” Tekmapro J. Ind. Eng. Manag., vol. 19, no. 2, pp. 194–205, 2024.

N. Saputra, E. Handayani, and A. Dwiretnani, “Analisa Penjadwalan Proyek dengan Metode Critical Path Method ( CPM ) Studi Kasus Pembangunan Gedung Rawat Inap RSUD Abdul Manap Kota Jambi,” J. Talent. Sipil, vol. 4, no. 1, pp. 44–52, 2021, doi: 10.33087/talentasipil.v4i1.48.

B. A. Prasetyo, H. Muhammadun, and L. D. Nugroho, “SCHEDULING ANALYSIS IN CONSTRUCTION WITH THE PERT METHOD USING MICROSOFT PROJECT,” Int. J. Sci. Technol., vol. 2, no. 3, pp. 84–91, 2023.

M. F. K. Amrullah, U. Budiarto, and A. F. Zakki, “Penjadwalan Proyek Reparasi Kapal Tugboat Selat Legundi II – 206 Dengan Metode Time Cost Trade-Off (TCTO) dan Project Evaluation And Review Technique (PERT),” J. Tek. PERKAPALAN, vol. 11, no. 1, pp. 105–115, 2023.

I. J. M, A. K. Hadi, and R. Musa, “Kajian Percepatan Durasi Pelaksanaan Pembangunan Gedung Utama Kantor Kementerian Agama Kabupaten Mamuju Pasca Gempa Provinsi Sulawesi Barat,” J. Konstr. Tek. Infrastruktur, dan Sains, vol. 01, no. 06, pp. 20–29, 2022.

S. Sutikno, E. Setiadi, and S. AR, “Analisis Percepatan Proyek Dengan Metode Pertukaran Waktu Dan Biaya (Studi Kasus Proyek Rehabilitasi, Peningkatan Dan Modernisasi Jaringan Irigasi SS. Pamanukan CS Kabupaten Subang),” J. Publ. Tek. Inform., vol. 2, no. 2, pp. 127–148, 2023.

A. H. Subakir and Sugiyanto, “Analisis Duration Cost Trade Off Untuk Mengejar Keterlambatan Pelaksanaan Proyek (Studi Kasus : Peningkatan Jalan Simorejo – Baureno Kabupaten Bojonegoro Jawa Timur),” Rang Tek. J., vol. 5, no. 1, pp. 8–23, 2022.

A. Kusumadwitya, I. P. Mulyatno, and O. Mursid, “Analisis Optimalisasi Waktu Dan Biaya Pada Proyek Pembangunan Kapal Angkut Tank 7900 DWT,” J. Tek. PERKAPALAN, vol. 11, no. 1, pp. 97–104, 2023.

Published
2025-01-13
How to Cite
Putri, F., & Nugraha, I. (2025). Optimizing Project Duration and Cost of Support Ship through Time-Cost Trade-Off Analysis and Microsoft Project Application: A Case Study at PT XYZ. Heuristic, 21(2), 173-186. https://doi.org/10.30996/heuristic.v21i2.12401
Section
Articles