Analisis Biaya dan Waktu pada Proyek Perumahan Citraland dengan Metode Percepatan Trade Cost Trade Off (TCTO) (Studi Kasus Perumahan Citraland Utara, Cluster North West Lake, Surabaya)

  • Alvin Antoro
  • Risma Marleno
  • Hanie Teki Tjendani
  • Esti Wulandari
Keywords: Residential, Late, Acceleration

Abstract

The growing human need for housing makes many developers compete to provide comfortable housing for people but limited land becomes a barrier to building these residences. Because of this land limitation, the housing project in Citraland North is also late to start work. Even though it started with delays due to land disputes, Citraland still had to provide the house on time so that the contractor was required to work extra in order to complete the housing on time. But sometimes in this housing development project there are obstacles that occur, one of which in this discussion is a land dispute that results in delays in the initial start of housing construction. From the work performance reports from PT Galaxy Alam Semesta, it is found that there is a delay in the work of the contractor CV Bangun Jaya Abadi so that acceleration is needed so that there is no delay. One way to overcome these delays is the Trade Cost Trade Off method. This method is a method of paying a number of additional costs to be replaced with overtime working hours or replaced as an additional number of workers. By also taking into account the critical points of the development process. In the citraland housing project undertaken by CV. Bangun Jaya Abadi, there was a delay of 108 days which must be resolved immediately so as not to be charged a fine for the delay. With the Trade Cost Trade Off method with additional labor, it is found that the project can be completed on time, namely within 297 days. With a cost of around Rp. 450,000.00.

Downloads

Download data is not yet available.

References

Anastasia Florensia Mela, 2016. Analisis Time Cost Trade Off Untuk Mengejar Keterlambatan Pelaksanaan Proyek (Studi Kasus: Pembangunan Hotel Zodiak Lampung, Pembangunan Hotel Park Inn By Radison, Pembangunan Toko Mitra Hasil Sentosa Di Bandar Lampung. Jurnal, Fakultas Teknik, Jurusan Teknik Sipil, Universitas Lampung.
Frederika, Ariany. 2010. Analisa Percepatan Pelaksanaan Dengan Menambah Jam Kerja Optimum Pada Proyek Konstruksi (Studi Kasus Proyek Pembangunan Super Villa, Peti Tenget, Badung). Jurnal, Fakultas Teknik, Universitas Udayana, Denpasar.
Iramutyn, Ermis Vera. 2010. Optimasi waktu dan biaya dengan metode crash (Studi Kasus Pada Proyek Pemeliharaan Gedung dan Bangunan Rumah Sakit Orthopedi Prof. Dr. R. Soeharso Surakarta). Tugas Akhir, Universitas Negeri Solo, Solo.
Mandiyo Priyo, 2016. Analisis Percepatan Waktu Dan Biaya Proyek Konstruksi Dengan Penambahan Jam Kerja (Lembur) Menggunakan Metode Time Cost Trade Off: Studi Kasus Proyek Pembangunan Prasarana Pengendali Banjir. Jurnal Ilmiah Semesta Teknika.
Kerzner, Harold. 2006. Project Management : A system Approach to Planning, schedulling, and Controlling, John and Wiley. Inc. Ninth Edition. New Jersey.
Soeharto, Imam, 2001, Manajemen Proyek, Jilid 2, Erlangga, Semarang Taha, H.A., 1996, Riset Operasi suatu pengantar, Jilid 2, Edisi kelima, Binarupa Aksara, Jakarta
Soeharto, Iman. 1999. Manajemen Proyek (Dari Konseptual Sampai Operasional). Penerbit: Erlangga, Jakarta
Soeharto, Imam 1997. Manajemen Proyek dari koseptual sampai operasional, Erlangga, Semarang.
Dipohusodo, Istimawan, 1996. Manajemen Proyek Konstruksi jilid 1, Kanesius, Jakarta.
Husen, Abrar, 2010. Manajemen Proyek, Andi, Yogyakarta.
Keputusan Menteri Tenaga Kerja dan Transmigrasi Nomor : 102/MEN/VI/2004 Tentang Waktu Lembur dan Upah Kerja Lembur.
Kodoatie, Robert. J., 1995. Analisis Ekonomi Teknik. Andi Yogyakarta, Yogyakarta
Widiasanti, Irika, dkk., 2013. Manajemen Konstruksi, Cetakan 1. PT. Remaja Rosda Karya, Bandung.
Published
2024-04-01
Section
Articles