ANALISIS BIAYA DAN WAKTU PADA PEMBANGUNAN GEDUNG TRAUMA CENTER DAN INTENSIVE CARE TAHAP IV RSUD DR. SOEDONO MADIUN DENGAN METODE EARNED VALUE

  • Nuri Maulidi Universitas 17 Agustus 1945 Surabaya
  • Hanie Teki Tjendani Universitas 17 Agustus 1945 Surabaya
Keywords: cost, time, earn value, estimate

Abstract

The earned value concept method can be used to analyze performance and estimate the achievement of goals. According to Auzan, et al (2017), there are three indicators in the concept of result value analysis, namely ACWP (Actual Cost of Work Performed) which is the actual cost of the work that has been carried out, BCWP (Budgeted Cost of Work Performed) which is a budget equal to the work performed. has been implemented, BCWS (Budgeted Cost of Work Schedule) is the amount of the budget for the planned work. In the research conducted on the Construction of the Trauma Center and Intensive Care Building Phase IV RSUD DR. SOEDONO Madiun, the data collection as research material was obtained from the implementing contractors and also some from the supervisory consultants. Time performance in the first week to week 7 (seven) obtained negative numbers for (SV) and (CV) meaning that the work was completed late and cost higher than the budget. While the value of SPI and CPI < 1, then the time performance is not good, meaning that the work is late from the planned schedule. The project performance is the same as the 

week 7 with a progress of -6.57%, the estimated cost required to carry out the project until it is completed is Rp. 64,938,243,717.90 means that there is a loss of Rp. 1,773,437,194.04 of the contract value. The estimated time for ETS (Estimate to Schedule) and EAS (Estimate at Schedule) until this project is completed (with a delay of –6.57% at week 7) are: ETS = 254 days = 36 weeks and EAS = 303 days = 44 weeks. So it can be concluded that if the project's performance is the same as the performance at the time of the review in week 7 of the planned 168 days or 24 weeks, it swells to 303 days or 44 weeks. This means almost double the planned time.

performance at the time of review in

Downloads

Download data is not yet available.

References

Auzan, Rifqi, dkk. 2017. “Pengendalian Biaya dan Waktu Proyek Dengan Metode Konsep Nilai hasil (Earned Value)” dalam Jurnal Karya Teknik Sipil Volume 6 No. 4
Chase, dkk. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Cronje, P. A. (2019). Earned Value Challenges in Projects With Different Project and Functional Currencies. In CCP EVP, 2019 AACE International Transactions, EVM-3265, AACE International.
Disti Mayang Sari, Nazwar Djali, I. K. (n.d.). PENERAPAN METODE KONSEP NILAI HASIL (EARNED VALUE CONCEPT) PADA GEDUNG BERLANTAI BANYAK.
Ervianto, WI. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Gardjito, E. (2017). Pengendalian Jadwal Dan Anggaran Terpadu Dengan Metode Earned Value Analysis Pada Pekerjaan Konstruksi. UKaRst, 1(1), 47–62.
Gupta, Randhika. 2014. “Earned Value Management System” dalam International Journal of Emerging Engineering Research and Technology Volume 2, Issue 4.
Hughes, Cotteral. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Kartikasari, Dwi. 2015. “Analisis Pengendalian Biaya dan Waktu dengan konsep nilai hasil (Earned Value) (Studi kasus :Fabrikasi Steel Structure Slag Storage Gresik)” dalam Jurnal Teknika No 1. Lamongan: Fakultas Teknik Universitas Islam Lamongan.
Maromi, M. I., & Indriyani, R. (2015). Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Pembangunan Condotel De Vasa Surabaya. Jurnal Teknik ITS.
Meliasari, I., & Indrayadi, M. (2014). (Studi Kasus Proyek Pembangunan Sarana / Prasarana Pengamanan Pantai) Earned Value Analysis Terhadap Biaya dan Waktu pada Proyek Konstruksi. Jurnal Teknik SIpil Universitas Tanjungpura, 1–11.
Nasution, Fauzy, dkk. 2015. “Penerapan Metode Konsep Nilai Hasil Dalam Pengendalian Proyek (Studi Kasus: Proyek Pembangunan dan pengadaan Utilitas Gedung Jasindo)” dalm Jurnal Departemen Teknik Sipil Sumatera Utara.
Nicholas. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Oberlender, Garold. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Olson. 2013. Pengertian Manajemen Proyek Menurut Para Ahli. https://kangnas.blogspot.com/2013/05/pengertian-manajemen-proyek.html. Diakses pada 11 Oktober 2018.
Sandhya, S., & Ganapathy Ramasamy, N. (2015). Analysis of Project Performance Using Earned Value Analysis. International Journal of Science, Engineering and Technology Research (IJSETR), 4(4), 1080–1085. https://doi.org/10.2754/avb200978040595

Vitriani. (2016). Analisis kinerja biaya dan waktu proyek pembangunan jalan akses.
Wahab, B. (2019). PENILAIAN PENGENDALIAN BIAYA DAN WAKTU PADA PROYEK PENINGKATAN JALAN MENGGUNAKAN METODE EARNED VALUE. Teras Jurnal. https://doi.org/10.29103/tj.v8i2.172
Witjaksana, B., & Reresi, S. P. (2012). Analisis Biaya Proyek Dengan Metode Earned Value Dalam Proses Kinerja (Studi Kasus Pada Proyek Pembangunan Universitas Katholik Widya Mandala Pakuwon Citi-Surabaya). Jurnal Teknik Sipil Untag Surabaya.
Published
2023-05-12
Section
Articles