ANALISIS PENJADWALAN PROYEK UNTUK MENGOPTIMALKAN WAKTU DAN BIAYA PENYELESAIAN PADA PT. DIMENSI ARSITEKTUR INDONESIA
Abstract
One of the constraints experienced in the implementation of the project
company is discrepancy between the schedule of the project implementation plan with
the state of the field, causing a delay in its completion, so the effect on the cost of the
project increased. This research was conducted by taking data time shedule of PT.
Dimensi Arsitektur Indonesia has undertaken the maintenance and painting of Tugu
Pahlawan Surabaya. From these data it can be calculated by using the critical path
CPM (Crithical Path Method) and software programs. On the use of CPM (Crithical
Path Method) stages of completion which is preparing an action plan, arrange network,
determine the forward and backward calculation, determining the spare time of
calculation. The project which is the object of the study authors is the maintenance and
painting of Tugu Pahlawan Surabaya that has been done by PT. Architectural
Dimensions Indonesia. PT. Architectural Dimensions Indonesia is a consulting services
company serving residential, lanscaping and interior but also engaged in the drainage
and road sector. In the drafting of planning time and costs during the company only
relied on the experience of work done on the previous project. From the planning that
has been done by the company, then do research to find out whether the plans made the
company so far has been optimal. The research method using descriptive research
where data collected by the researchers by means of direct observation of companies
and interviews, then from the data obtained researchers performed data processing and
analysis, so as to obtain an overview of the planning time and costs that may be
considered by companies as well as can be to be completed by the company. Based on
the results of research and calculations by network planning using CPM (crithical path
method), it can be concluded that the planning time and cost network planning to use it
by using critical path method CPM appropriate to be applied in the company at the
time of planning and project cost, because it optimizes the time and cost of the project.
More efficient project time 6 days or by 9.67% and the cost of the project is also
efficient Rp 17,709,597.6 or equal to 9.67%.
Keywords: Project Scheduling, CPM, Optimization
Downloads
References
Arikunto. S. 2007. Manajemen
Penelitian. Jakarta: PT.
Rineka Cipta.
Ataki. 2008. Hampir Empat Juta
Tenaga Kerja Konstruksi
Sulit Mendapatkan Sertifikat.
http://www.ataki.org, diakses
Januari 2016.
Gitosudarmo, Indriyo. 2002.
Manajemen Operasi. Edisi
Kedua. Yogyakarta BPFE
Yogyakarta
Haming, Murdifin dan Nurnajamuddin,
Mahfud. 2007. Manajemen
Produksi Modern Operasi
Manufaktur dan Jasa. Jakarta:
Bumi Aksara.
Handoko, Hani. 2000. Dasar-Dasar
Manajemen Produksi dan
Operasi. Yogyakarta : BPFE
Heizer, Jay dan Render, Barry. 2006.
Operations Managemen. Edisi
Ketujuh. Terjemahan
Setyoningsih,
Dwianoegrahwati dan
Almahdy, Indra. Jakarta:
Salemba Empat
http://repository.usu.ac.id/bitstream/123
/35193/4/Chapter%20II.pdf
http://www.swa.co.id/sekunder/kolom/
manajemen/strategi/index.php/
http://vutrav4.blogspot.com/2013/02/teo
ri-management-menurut-para-ahli.html
JEM17
Jurnal Ekonomi Manajemen, Hal 1 - 16
Volume 1, Nomor 1, Mei 2016
Husen, A. 2009. Manajemen Proyek.
Yogyakarta: Penerbit Andi
Sertifikat.
Ma’arif, Syamsul Mohamad dan
Tanjung,Hendri. 2003.
Manajemen Operasi. Jakarta:
Grasindo
Nurhayati. 2010. Manajemen Proyek.
Yogyakarta: Graha Ilmu
Prasetya, Hery dan Lukiastuti, Fitri.
Manajemen Operasi.
Yogyakarta: MedPress
Santosa, Budi. 2009. Manajemen
Proyek. Yogyakarta: Graha
Ilmu
Setianingrum, Ginanjar. 2011. Analisis
Dan Simulasi Percepatan
Aktivitas PERT (Program
Evaluation and Review
Technique).
Soeharto, Iman. 2002. Studi Kelayakan
Proyek Industri. Jakarta:
Erlangga
Authors whose manuscript is published will approve the following provisions:
- The right to publication of all journal material published on the JEM17: Jurnal Ekonomi Manajemen website is held by the editorial board with the author's knowledge (moral rights remain the property of the author).
- The formal legal provisions for access to digital articles of this electronic journal are subject to the terms of the Creative Commons Attribution-ShareAlike (CC BY-SA) license, which means JEM17: Jurnal Ekonomi Manajemen reserves the right to store, modify the format, administer in the database, maintain and publish articles without requesting permission from the Author as long as it keeps the Author's name as the owner of Copyright.
- Printed and electronically published manuscripts are open access for educational, research, and library purposes. In addition to these objectives, the editorial board shall not be liable for violations of copyright law.